Summarized Float

3 replies [Last post]
Rajeev Kumar
User offline. Last seen 9 years 32 weeks ago. Offline
Joined: 27 Apr 2003
Posts: 43
Groups: None
Can someone tell me what does the summarized float mean?Any help would be appreciated. Thanks

Replies

Frank Borcherdt
User offline. Last seen 7 years 41 weeks ago. Offline
Joined: 3 May 2001
Posts: 88
Groups: None
When you summarize data using format organize, P3 also keeps track of the earliest calculated early start, earliest calculated late start, latest calculated early finish and latest calculated late finish for that group of activities. Philip is right that there is an option to determine how the total float is calculated BUT be very careful before you change it from finish dates (the default method used by most software including SureTrak) as it will apply it to all activities as well as the summaries.

If you leave the option on finish dates it’s the latest calculated late finish for that group of activities less the latest calculated early finish for that group of activities, on start dates it’s the different between the start dates, most critical is the smallest of the start or finish float.

As long as you understand that it applies to float calculations at both the summary and detail levels chose the method that suits your particular circumstance. I tend to leave it on finish dates for compatibility with other products including Suretrak.
Philip Jonker
User offline. Last seen 15 years 43 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi Guys,

As I have never heard this term, I had a look in the help menu. This topic is actually covered in the P3 Help menu, under "How P3 summarizes data". Apparently you can set some options. I would say that if a group of activies is summarized, the summarized float should be that of the activity with the least float in the group. Therefore I would set the option to "most critical dates".

Lets hear some other opinions on the subject.

Regards,

Philip
Daniel Limson
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None
Summarized float would be the total float available to your project, again which means the total aggregate number of days you can delay a project without affecting your completion date.

Regards,
Daniel