Store Period Performance - Calendar Months

1 reply [Last post]
Martin Kerr
User offline. Last seen 7 years 19 weeks ago. Offline
Joined: 3 May 2017
Posts: 2
Groups: None

I have a new client who have just invested in P6 for the first time (R16.2)

I am in the preocess of setting up to record earned value. Not currently looking to record actuals in P6.

The clients reporting calendar is aligned to calendar months.

Do I have to set up reporting periods aligned to calendar months manually in order to store period performance or is there a quick way to do this?

'Batch Create Financial Periods' doesnt appear to have options for calendar months.

 

Thanks

 

Martin

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 19 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

set up the financial periods there is a batch create in versin 6.2

then perform a stoer period peformance prior to updating the next period