Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

BL PROJECT FINISH DATE IN P6

3 replies [Last post]
Tanveer Ahmad Niazi
User offline. Last seen 7 years 7 weeks ago. Offline
Joined: 15 Dec 2005
Posts: 151
Groups: GPC Qatar

Hi,

We got an EOT approved and submitted the last updated program complying the new project finish date. I submitted the updated schedule as the revised baseline. Now when I maintained the baseline (Save a Copy The Current Project) and assigned accordingly I inserted the columns “BL Project Start” and “BL Project Finish” I am getting a date 93 days later then the data date. Then I updated the schedule at the current dated, and  the finish of project projected to 45 days ahead of current date but the BL Project Finish is still the same (93 days ahead of our cutoff date). I removed the baseline and deleted from the data base but those dated are still there.

How can I show the new project finish date in the BL Project Finish column?

Cheers - Tanveer

Replies

Tanveer Ahmad Niazi
User offline. Last seen 7 years 7 weeks ago. Offline
Joined: 15 Dec 2005
Posts: 151
Groups: GPC Qatar

Thank you guys, that helped me alot

Gary Whitehead
User offline. Last seen 5 years 49 weeks ago. Offline

Also worth checking your admin settings to ensure you are showing baseline and not planned dates -see link below

http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf

Feng Benjamin
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 1 Feb 2011
Posts: 12
Groups: None

Hi,

From what I understand of your description, it is just a matter of refreshing your schedule using "F5" function.

Once you do that, the dates should revert to the project finish date you require.

 

Regards,

Benjamin