Resourse assignments in P6 Ver 7

1 reply [Last post]
Nilkamal Parikh
User offline. Last seen 1 year 32 weeks ago. Offline
Joined: 13 Jul 2009
Posts: 31

Hi,

I am a new user of P6 version 7. I want to prepare the program with resourses on it. I am not sure what I am doing is correct or not but I am explaining here to you all (Expert & well experienced Planners) for your comments:

I create a material resourse with the estimated production rate of units/day and assign that to the activity. The activity duration type I keep is "Fixed Units/time". Then I give budgeted quantity so the durations are derived from that. If I change the budgeted quantity the durations will change by its own.

Now my problem is, while creating the resourse I set certain production rate for that and I assign to the activity. But if I change the production rate of the resourse, it doesn't change to the assignments by its own. I have to remove the resourse assignment & reassign the same resourse again which is very boring and time consuming task. I am surer there must be some other way to do all at the same time. Can any body direct me how to do that?

Thanks

Nilkamal

Replies

Tanveer Ahmad Niazi
User offline. Last seen 7 years 7 weeks ago. Offline
Joined: 15 Dec 2005
Posts: 151
Groups: GPC Qatar

Hi, Nilkama,

I am also new in planning and working on P6v7. Would you please tell me where did you enter/set the production rate, coz I didn’t find any column or tab for this,

Thanx & Cheers

Tanveer