Export to Excel

2 replies [Last post]
moutaz aldeib
User offline. Last seen 2 years 49 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Greetings Planners,

I am exporting project to excel from P6, the project includes 4 levels of WBS and when I export the project to Excel, it considers only the last level, how can I show all levels in Excel?

regards,

Muataz

Replies

Santosh Bhat
User offline. Last seen 18 weeks 4 days ago. Offline
Joined: 15 Apr 2005
Posts: 381
Moutaz, From within P6, in your activity view, select all activities (CTRL+A) l, then copy to your clipboard (CTRL+C) and then just paste into excel. this will retain.th3 grouping you're displaying if you need to keep the activity ids aligned, here is a quick tip i wrote recently: https://www.linkedin.com/feed/update/urn:li:activity:6746658764419670016
Mohammed Ali
User offline. Last seen 2 years 16 weeks ago. Offline
Joined: 16 Mar 2018
Posts: 72
Groups: None

Hi Moutaz

You can use the WBS Magic Tool, it's an amazing tool to display, modify and export the WBS between excel and Primavera.

This is the link:

http://www.planningplanet.com/forums/oracle-primavera-pm6/866651/get-wbs-magic-tool-it%E2%80%99s-free