Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Can we avoid project delays caused by bad weather?

8 years 3 days ago

Has your project been delayed by bad weather?

Contractors are an eternally optimistic bunch and never seem to allow for any weather related impacts on construction projects. What, - are you really going to work on a twelve month long project and think you won’t encounter rain, winds, summer, and winter at some stage in the course of your project! If you have 500mm (20

Read more...
 
General

Create P6 resources dictionary using excel without using SDK

8 years 5 days ago

The SDK (Software Development Kit) is an awesome tool that allow P6 database to connect to excel and exchange information in order to create the schedule using excel. But sometimes the SDK is not installed on the Primavera machine and the scheduler doesn’t have the privilege to install it or the resource sheet in the SDK is not working with P6 version that the scheduler has. In this article I

Read more...
 

Time Equals Money

8 years 1 week ago

We have all been told that time equals money. Even, time is money. But what does any of that truly mean? Time and money separately are highly debatable subjects. The combination of the two can certainly be a conundrum. However, it is this author’s belief that in construction, this may as well be a law of the universe. Consider this. He or she who controls the schedule of the project

Read more...
 

What you need to know to close-out your construction project successfully

8 years 1 week ago

Many construction projects are financially successful until the end, when costs suddenly spiral out of control. The main reason for the additional costs is because the project isn’t completed on time. When I say completed, I don’t just mean handed over, I mean one hundred percent finished.

I’ve visited projects long after they have been completed, yet the contractor’s offices and workers

Read more...
 
General

How to update Baseline in Primavera P6

8 years 3 weeks ago

Baseline is something we usually do not change. However in some case we need to change it.

I will show you how to do it.

We have a simple project which is assigned a baseline

Read more...
 

Detect changes made to calendars between two projects in P6

8 years 3 weeks ago

The Claim digger or Schedule Comparison is a widely used tool in P6 to compare between two projects and detect the differences.

One of the main shortage of the Claim Digger or the Schedule Comparison tool is detecting the changes in calendars.

The tool will not detect any revisions in calendars working hours or changing from Project to Global calendar if both have the same

Read more...
 

Time: Conserving the Precious Resource

8 years 3 weeks ago

Time is the dominant constraint on all projects.  There is a constant race against the clock.  Many projects have fixed completion dates determined by external forces. Projects that fall behind schedule, struggle to catch up.  I have never met a project manager who said there was too much time.

"Time is also a unique resource. One cannot rent, hire, buy,

Read more...
 

Egad! It is the Most Likely Schedule!

8 years 3 weeks ago

Most Likely Schedule, what is it?

It is one of the questions asked more often in risk-based planning and scheduling (Related topic: Data Maturity, Quality and Project Integration).  Project directors, managers, planners, and schedulers have to know what this term means.

Each time a scheduler tries to explain the concept, he easily gets lost in

Read more...
 

Determine the longest path of a resource leveled schedule in P6

8 years 4 weeks ago

Unfortunately when it comes to resources and resource leveling, P6 model is absolute. P6 doesn’t calculate the float correctly and the longest path will not be accurate since the late and early dates will not change after leveling.

Primavera P6 doesn’t take in consideration the new dates after the leveling in calculating the total float or the longest path, to illustrate further if we

Read more...
 

The story behind the negative float in P6

8 years 4 weeks ago

The negative float is a very popular hot topic in the scheduling field and it’s generated when the late dates are less than the early dates and usually it’s accompanied with a delay in the project, and a lot of project management professionals think that the only reason for a negative float is because a constraint that has been used in the schedule. Although the first thing you look for when

Read more...
 

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.